Price/Quality Trade-Off Models

By Barb Rebola and Suzanne Findlay, Procurement Associates

Lowest price is not value for money. So why do we keep scoring it as if it were?

At Procurement Associates, we don’t weight price. Ever. When we manage the price/quality trade-off in a procurement, price doesn’t get a percentage weighting alongside the quality criteria. We judge quality on its own merits, then assess price separately, as a value-for-money test.

Here’s why, and how it works in practice.

Price has gravity. Every evaluation feels its pull: a quiet drift toward the cheapest number that nobody on the panel actually decided to follow.

The panel agrees that quality matters. The criteria are set, non-price criteria get 60 per cent of the weighting and price gets 40. Every tender is scored, the spreadsheet adds it all up, and a winner appears at the top. Then someone asks why that tender won, and the honest answer is often: because the formula said so.

Why price keeps winning

Nobody sets out to buy on price alone. Even WA’s local government tender regulations ask which tender would be the most advantageous to accept, not which one is cheapest.

And yet price has a habit of winning anyway. Not because anyone decided it should, but because of what each number is.

Quality is a judgement. Price is a fact.

When responses are close, when the deadline is looming, or when someone senior asks “why are we paying more?”, the fact feels safer than the judgement. So the decision drifts toward price. Not deliberately. Just gravitationally.

Weighted scoring is supposed to be the defence against that drift. In practice, it’s where the drift happens.

How weighted scoring is meant to manage the trade-off

Weighted scoring is the usual tool for managing the price/quality trade-off. You set out your non-price criteria (sometimes called qualitative criteria), such as relevant experience, methodology, key personnel and capacity. You give each one a percentage weighting, score each tender against each criterion, then multiply and add to get a total.

Many buyers also put price into the same calculation, as one more criterion with its own weighting: 70/30, 60/40 or 80/20.

Weighting the quality criteria has one real merit. It makes you declare your priorities before you see the responses, when you can’t yet be tempted to bend them toward a supplier you’ve started to favour. That discipline is worth keeping. Putting price into the same sum is where it goes wrong.

The weak point is price. A tender’s quality can be scored against criteria. A price can’t. It’s a dollar figure, so it has to be converted into points, and that needs a formula. Two common ones are:

  • Relative to the lowest price: the lowest price gets full marks, and every other tender gets the lowest price divided by its own price, multiplied by 100.
  • A lowest-to-highest scale: the lowest price gets 100, the highest gets zero, and everything in between is scored in proportion.

Both look reasonable. Neither is safe.

Where weighted price scoring breaks

Same tenders, same weightings, different winner

Take a simple hypothetical. Quality is weighted at 60 per cent and price at 40 per cent. Tender A scores 90 out of 100 on quality, at $500,000. Tender B scores 60 on quality, at $450,000. (All prices in this article exclude GST.)

Price formulaTender A totalTender B totalWinner
Relative to the lowest price90.076.0A
Lowest-to-highest scale54.076.0B

Nothing changed except the arithmetic. Under one formula, A wins comfortably. Under the other, B does.

A tender that can’t win can still change who does

Now add Tender C, which scores 50 on quality at $700,000. C was never going to win. But under the lowest-to-highest scale, C becomes the highest price, which lifts A’s price score from zero to 80.

The totals become A 86.0, B 76.0 and C 30.0. A now wins.

Nothing about A or B changed. The arrival of an uncompetitive tender flipped the result between them. This is sometimes called rank reversal.

One low bid can set the ruler for everyone

The relative-to-lowest formula has the same weakness in a different form. The lowest price sets the scale that everyone else is measured against. If that price comes from a tenderer who has under-scoped the work, misread the brief or simply made a mistake, an unrealistic number becomes the ruler for every serious bidder. A single low-ball bid can skew the scores of every other bid.

In each case, the evaluation isn’t really comparing A with B. It’s comparing each tender with the rest of the field, and the field is something you don’t control.

Other formulas, such as scoring against the average price, have their own flaws. There is no good formula for turning price into points, so we don’t use one.

Our approach: judge quality first, then test value for money

Non-weighted price evaluation separates two questions that weighted scoring blends together. How good is each offer? And is it worth the price?

Score quality on its own merits

The panel scores the non-price criteria only, and weights them to 100 per cent. Each tender is scored against fixed descriptors set before tenders open, describing what a strong, adequate or weak response looks like for each criterion.

The descriptors matter. If tenders are scored relative to the best submission received, the field starts influencing results again. Scored against fixed descriptors, Tender A is a 90 and Tender B is a 60 whoever else bids. Tender C’s arrival changes nothing.

Compare prices directly

Price isn’t converted into points. We compare each respondent’s price as it stands, on a like-for-like basis: A at $500,000, B at $450,000 and C at $700,000.

Look past the headline price

The tender price isn’t always the whole cost. A cheaper offer from a supplier who has under-scoped the work can bring a longer learning curve, a shaky mobilisation or an early variation once real conditions show up. The low price hasn’t removed that cost. It has moved it off the page and into the life of the contract.

So when you compare prices, ask what each offer is likely to cost over the term, not just what it says at award. This is where the quality assessment earns its keep, because it tells you how much of that risk each offer carries.

Ask the value-for-money question openly

Now the real question is on the table: is Tender A’s quality advantage worth $50,000 more than Tender B?

The answer depends on what that difference in quality actually represents. A stronger methodology for high-risk work, or a more experienced team for a service where failure is expensive, may well be worth the extra. For a simple, low-risk purchase, it may not. Tender C offers lower quality at the highest price, so it has no value case to make.

This approach doesn’t make the decision easier. It makes it visible. The panel weighs the quality difference against the price difference, makes a judgement and records its reasons. Those reasons can be read, questioned and explained. A formula can’t do any of that.

Comparing prices when the pricing gets complicated

Sometimes the price comparison is straightforward: one lump sum from each respondent. Often it isn’t. A tender might ask for a schedule of rates, dozens of line items, optional extras or provisional quantities. Respondents may also make different assumptions about what’s included.

When that happens, the totals as submitted may not be comparable. We use a structured comparison, usually a spreadsheet, that sets each respondent’s prices side by side item by item and builds up to a total excluding GST. A good comparison:

  • applies the same quantities to every respondent’s rates, so totals are built on the same basis
  • checks the arithmetic and flags any errors
  • identifies missing items, exclusions and qualifications that would change the real cost
  • normalises for gaps, adding a fair allowance for any missing or excluded item (usually based on the other respondents’ rates or a pre-tender estimate) so every total covers the same scope, without changing the tender itself
  • compares totals excluding GST, so every offer is measured the same way.

Where something in a tender is unclear, the respondent can be asked to clarify it. Clarification is about understanding what was offered, not an opportunity to re-price. Any normalising adjustment should be recorded, with its basis, in the evaluation report.

Defending the decision to approvers

Panels often retreat to price for a simple reason: they’re worried about the conversation with whoever signs the approval.

“Why didn’t we choose the cheapest compliant tender?” is a question every panel should expect. If you can’t answer it crisply, you risk losing the argument, and the better supplier with it.

The answer isn’t that the panel liked them more. It’s a documented trail, most of it written before tenders closed:

  • How price will be assessed, decided before tenders are invited and explained to tenderers.
  • Quality descriptors that show what evidence earns each score.
  • Quality scores settled before price comes into the discussion, so a low price can’t colour how the panel reads the quality evidence.
  • A like-for-like price comparison, including what each offer is likely to cost over the contract, not just at award.
  • A clear statement of the trade-off: this is the extra capability, this is the extra cost, and this is why the organisation is better off paying for it.

The test: if an approver asks why you didn’t take the lowest price, you should be able to answer in three sentences, from documents that existed before you knew who won.

For WA local governments

The documented trail matters for compliance as well as good practice. Under the Local Government (Functions and General) Regulations 1996, a local government must decide in writing, before tenders are publicly invited, the criteria for deciding which tender should be accepted (regulation 14(2a)). Those criteria form part of the detailed information available to tenderers (regulation 14(4)(c)). Tenders are then assessed through a written evaluation against those criteria, and the local government decides which tender would be most advantageous to accept (regulation 18(4)).

The tendering provisions don’t set weightings or require price to be a weighted criterion. So a separate value-for-money assessment fits the framework, provided it’s written into the criteria from the start. “We’ll look at price afterwards” is not enough.

The same discipline suits private-sector and not-for-profit buyers, even where no regulation applies. Whoever signs off the decision should be able to see how it was made.

When the decision is mostly about price

None of this is an argument against price. Price matters, and paying more than you need to is its own kind of failure.

For standard goods or simple services, every compliant offer may deliver much the same quality. The quality assessment then separates very little, and the price comparison will largely decide the outcome.

That’s fine. Even here, we don’t weight price. The method stays the same, and quality simply carries less of the decision. What matters is that the evaluation fits the purchase, and that the effort is proportionate to the value and risk involved.

Before you release your next tender: five questions

  1. Have we written down how price will be assessed, and will tenderers know?
  2. Are our quality descriptors fixed, so each tender is scored on its merits rather than against the best one we receive?
  3. Is our pricing schedule set up so responses can be compared line by line and totalled on the same basis, excluding GST?
  4. Do we know what a quality difference would need to look like to justify paying more?
  5. Could we explain the decision to an approver in three sentences, without pointing at a formula?

Price has gravity. The answer isn’t to score it more cleverly. It’s not to score it at all. We keep price out of the weighted score every time, judge quality on its own merits, and make the value-for-money decision as a step of its own, in the open.

This is Article 3 in The Procurement Toolkit, Procurement Associates’ series on practical tools for complex, high-value procurement. Article 1 covers early contractor involvement and interactive evaluation, Article 2 covers key personnel clauses and retention mechanisms. Next month, Article 4 looks at market sounding and industry engagement.